Why is the concrete limited to a placement height or lifts of 4 feet (1.2 m)?
To alle­vi­ate the pres­sure from the liq­uid con­crete, the con­crete is placed in lay­ers or lifts’. The first lift is lim­it­ed to 4′ (1.2 m) of con­crete around the perime­ter of the build­ing. This allows approx­i­mate­ly one hour for the con­crete to set-up before con­tin­u­ing with the next 4′ (1.2 m) lift. The low­er lift pro­vides sup­port for the next lift as the con­crete is placed con­tin­u­ous­ly around the build­ing in con­sec­u­tive lifts to the top of the wall.
How do I determine which size ICF to use?

ICFs pro­vide a rein­forced con­crete wall which is designed to spe­cif­ic engi­neer­ing prin­ci­ples. Typ­i­cal res­i­den­tial con­struc­tion, per the applic­a­bil­i­ty lim­its in the build­ing code, allows walls 10′ (3 m) high or less between lat­er­al sup­ports (floor and roof con­nec­tions). Below grade walls must have a min­i­mum 6″ (150 mm) con­crete core. In some regions, an 8″ (200 mm) con­crete core is the min­i­mum allowed thick­ness for below grade walls.

The 4″ (100 mm) form can­not be used below grade as a foun­da­tion wall. The 4″ (100 mm) form may be used for above grade walls up to a max­i­mum of 10′ (3.0 m).

The 6″ (150 mm) form, above grade, is lim­it­ed to approx­i­mate­ly 14′ (4.2 m) in height. Walls high­er than 14′ (4.2 m) must use an 8″ (200 mm) or larg­er form.

Typ­i­cal res­i­den­tial con­struc­tion will use 6″ or 8″ con­crete core size blocks. Project spe­cif­ic engi­neer­ing may allow for some core thick­ness to span ver­ti­cal­ly high­er than these pro­posed guide­lines.

What is a ‘blow-out’?

A blow-out’ is a break in the form, gen­er­al­ly due to the pres­sure from the liq­uid con­crete dur­ing the con­crete place­ment and/​or con­sol­i­da­tion. Fox Blocks ICFs are designed to main­tain a high safe­ty fac­tor of pres­sure from the liq­uid con­crete. Dam­aged forms or fail­ure to sup­port areas where forms have been cut leav­ing a large area of EPS between the web sup­ports may cause a blow-out. Over con­sol­i­da­tion may also cause a blow-out.

Fox Blocks rec­om­mends the Pre-Place­ment Check­list be reviewed for all wall assem­blies pri­or to the place­ment of con­crete, to find poten­tial prob­lem areas and install addi­tion­al strap­ping or sup­port to pre­vent blow-outs. Gen­er­al­ly, for an Fox Blocks form, the size of a blow-out may be lim­it­ed to the EPS between the webs, 6″ or 8″ wide by the height of one form. If a blow-out occurs, the con­crete pour moves to anoth­er area on the wall, the hole is patched by replac­ing the EPS, installing wood sup­port over the area, and then resum­ing the pour.